GR Critical Notice

Notice ID: 62325
Notice Type: MAI
Critical: Y
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2026-03-13 08:32:00.0
Subject: Golden Pass Pipeline Planned Maintenance
Notice Effective Date/Time: 2026-04-21 09:00:00.0
Notice End Date/Time: 2026-05-23 00:00:00.0
Notice Text:

This Action Alert is being issued pursuant to Section 7, GT&C, of Gulf Run’s Tariff to notify shippers of unplanned maintenance at Gulf Run’s Golden Pass Pipeline (808311) meter located in Calcasieu Parish, Louisiana and in Gulf Run’s Zone 2.

This planned maintenance will begin Tuesday, April 21st, 2026, at 09:00 with a completion date of April 22nd, 2026, at 09:00

 

During this maintenance, deliveries to Golden Pass Pipeline (808311) will be limited to 0 Dth/D.

 

Gulf Run does anticipate impacts to its primary firm services. Should any of the details of this posting change, Gulf Run will notify its shippers and update this notice accordingly. Gulf Run will schedule nominations, if needed, on each impacted day in accordance with its tariff. This alert will remain in effect until the completion of the maintenance.

If you have any questions concerning this alert, please contact your Scheduling Representative.