Notice ID: | 8492 |
Notice Type: | GEN |
Critical: | Y |
Notice Status Description: | |
Reqrd Rsp Desc: | |
Posting Date/Time: | 2019-12-06 08:36:00.0 |
Subject: | Stingray Return to Service Update #2 |
Notice Effective Date/Time: | 2019-12-06 08:36:00.0 |
Notice End Date/Time: | 2200-01-01 00:00:00.0 |
Notice Text: |
12/06/2019 - Stingray Return to Service Update #2
Updates to this Posting are in bold.
The pigging operations intended to verify the pipeline integrity of the Stingray 36" mainline are nearing completion. The Smart Tool runs have been completed, and we are preparing the system to return to service.
Effective Gas Day December 7, 2019, receipt locations upstream of Platform 509 will be able to resume flow, and nominations will be accepted.
At this time, the only operationally available delivery location is Bridgeline, Stingray Meter 94200.
However, receipt locations downstream of Platform 509 will be delayed until the sub-sea valves are opened on the respective laterals; we anticipate being able to accept nominations for flow for Gas Day December 11, 2019 for these locations.
Stingray will update this posting and confirm the available flow days for all locations when the system is ready and nominations will be accepted.
Any questions should be directed to Jennifer Merkel at 713-989-7649.
|