Notice ID: | 350 |
Notice Type: | PSO |
Critical: | N |
Notice Status Description: | |
Reqrd Rsp Desc: | |
Posting Date/Time: | 2015-09-01 05:32:14.0 |
Subject: | Planned Service Outage – West Cameron 565 Peregrine (PIN 600565) Abandonment - Update 3 |
Notice Effective Date/Time: | 2015-09-07 04:00:00.0 |
Notice End Date/Time: | |
Notice Text: |
The scheduled maintenance associated with abandonment procedures at the West Cameron 565 Peregrine (PIN 600565) platform (See Notice ID 336) has been further delayed. The associated 3rd party contractors will not arrive to the site until September 7, 2015.
The possible delay due to the pigging operations associated with this abandonment have been resolved (see Notice ID 349).
The duration of this project is expected to be approximately 2 to 3 weeks. Weather and other factors beyond Stingray’s control may hinder or expedite the progress of the work.
The following platforms will have to shut in for the duration of the work beginning at 9:00 AM CCT Monday, September 7, 2015.
Garden Banks 189 Chevron (PIN 400189) Garden Banks 668 Gunnison (PIN 400668) HI-A330 HIOS/STINGRAY (PIN 70A330) West Cameron 544 Arena Offshore (PIN 600544) West Cameron 548 Arena Offshore (PIN 600548) West Cameron 552 Black Elk (PIN 600552) West Cameron 616 W&T Offshore (PIN 600616) West Cameron 661 Tarpon (PIN 600661)
Any additional information regarding changes to contractor schedules, or weather related delays, will be posted as necessary.
For questions concerning this notice, please contact Transportation Services at (713) 457-8990.
|