Notice ID: | 9197 | ||||||||||||||||
Notice Type: | GEN | ||||||||||||||||
Critical: | Y | ||||||||||||||||
Notice Status Description: | |||||||||||||||||
Reqrd Rsp Desc: | |||||||||||||||||
Posting Date/Time: | 2021-10-07 09:55:00.0 | ||||||||||||||||
Subject: | Sea Robin West High Liquids Final Update | ||||||||||||||||
Notice Effective Date/Time: | 2021-10-07 09:55:00.0 | ||||||||||||||||
Notice End Date/Time: | 2200-01-01 00:00:00.0 | ||||||||||||||||
Notice Text: |
10/07/2021 Sea Robin West High Liquids Final Update Sea Robin Pipeline Company has been informed by Fieldwood Energy, operator of the Condensate Removal Facility, that the produced water issues have been resolved. Effective Gas Day October 7, 2021, Sea Robin will be accepting nominations from all locations except for the following:
The following meters are still under Force Majeure, as per Critical Notice 8876, and must remain shut in:
In addition, Sea Robin Gas Processing Plant, operated by Enterprise, will resume processing operations once there is sufficient throughput but will dehydrate the gas. At this time, PTR nominations will not be accepted. Shippers are required to contact their downstream delivery point operators to confirm their ability to accept the unprocessed gas from Sea Robin. Receipt point nominations will not be accepted until downstream deliveries are confirmed. Updates will be posted as they become available. If you have any questions, please contact your Marketing or Customer Service Representative. |