Start Date
|
End Date
|
Title
|
Location
|
Type of
Work
|
Impact
|
SPW
|
4/8/2025
|
4/15/2025
|
Vernon
Spring Maintenance
|
Pipe -
Buckley
|
Annual
Maintenance
|
8
|
52178
|
4/11/2025
|
4/11/2025
|
Gulf Run
(Westdale to Deridder) Cleaning Pig
|
Westdale
|
Cleaning
Pig
|
1
|
|
5/1/2025
|
5/31/2025
|
Panola
Station Unit 2 (Turbine Replacement)
|
Other
|
Regular
Maintenance
|
3
|
|
6/10/2025
|
6/14/2025
|
Gemini CP
Panola
|
Gemini
|
RTU
Installation
|
8
|
52474
|
7/8/2025
|
7/12/2025
|
Marlin to
CP
|
Marlin
Midstream
|
RTU
Installation
|
8
|
52475
|
7/15/2025
|
7/19/2025
|
Midcoast
to CP (1-220020)
|
Enbridge
|
RTU
Installation
|
8
|
52476
|
TBD
|
TBD
|
Golden
Pass PLC Upgrade
|
Golden
Pass
|
RTU
Installation
|
1
|
|
|
|
|
|
|
|
|
1. No
capacity impact is expected at this time.
|
2.
Coordinating with necessary loads.
|
3. Based
on historical and current throughput, no capacity impact is expected. In the
event nominations increase significantly, restrictions may become necessary.
|
4.
Coordinating maintenance with interconnecting pipe to minimize customer
impact. No capacity impact is expected at this time; however, if operating
conditions change, affected parties will be notified.
|
5.
Affected production notified of shut-in during work.
|
6.
Customers may experience pressure fluctuations, but no capacity impact is
anticipated.
|
7. Based
upon customer nominations, restrictions may become necessary.
|
8. Based
on all available information, capacity will be impacted. Capacity reductions
will be done in accordance with the provisions of GR's tariff regarding
scheduling and interruption of services.
|