FIRM TRANSPORTATION CAPACITY POSTING
|
Thursday, May 23, 2024
|
|
|
|
|
Gulf Run
Transmission, LLC ("GRT") is providing notice to Shippers and
potential Shippers of available firm capacity for the period(s) noted below.
|
Written requests for firm capacity, in accordance with
GRT's FERC Gas Tariff, should be received by GRT in order to be evaluated.
Please submit your request to dlGulfRunCommercial@energytransfer.com. Contact
your GRT Marketing Representative for more information.
|
The available capacity shown assumes receipts from the
furthest upstream point in the receipt area. Receipts from points further
downstream could provide additional available capacity. Available capacity
from specific receipt points to specific delivery points are subject to the
available capacity at the specific points.
|
Available Firm Transportation Capacity (in Dth/d)
|
|
May-2024
|
June - Oct 24
|
Nov 24 - Mar 25
|
Deliveries
to Zone 1
|
|
|
|
Receipts from
Carthage Area
|
0
|
0
|
0
|
Receipts from
West Haynesville Area
|
0
|
0
|
50,000
|
Receipts from
East Haynesville Area
|
0
|
0
|
135,000
|
** Capacity
available to meter GR Zone 1 to Zone 2 (GRZ1Z2) from East Haynesville and PVH
|
|
|
|
|
Deliveries to Zone 2
|
Receipts from Carthage Area
|
0
|
0
|
0
|
Receipts from
West Haynesville Area
|
0
|
0
|
50,000
|
Receipts from
East Haynesville Area
|
50,000*
|
50,000*
|
50,000*
|
The available
capacity shown from receipts in the Carthage Area, West Haynesville and East
Haynesville are mutually exclusive
* Capacity is also available from West Haynesville Area at Kinderhawk
(220325) receipt point only (Subject to available meter capacity).
|
|
|
|
|
Receipts from Perryville Receipt Area
|
Deliveries to
Zone 2
|
50,000
|
50,000
|
50,000
|
Deliveries to
Zone 1 East Haynesville Area
|
390,000
|
390,000
|
390,000
|
Deliveries to
Perryville Area
|
Meter Point
Capacities**
|
Meter Point Capacities**
|
Meter Point Capacities**
|
** Refer to
specific receipt and delivery point available capacity
|
|
|
|
|
Deliveries to HPL
|
Receipt from
ST-1 Monument/Waskom
|
25,000
|
25,000
|
25,000
|
Receipts from
Carthage Area
|
130,000
|
130,000
|
130,000
|
The available
capacity shown as deliveries to HPL are mutually exclusive
|
|
|
|
|
Award of capacity from a particular receipt or delivery
area may affect the potential capacity available in another area. Requested
deliveries will have to be evaluated by receipt location, delivery point and
time period. GRT’s ability to accept a request and provide a given service
is subject to and based on the location and volume of existing and projected
receipts and existing and projected deliveries on the total GRT system during
this period. GRT will consider requests offering rates different from GRT's
maximum FERC-approved rates for the capacity and will evaluate such completed
requests pursuant to Section 16 of the General Terms and Conditions of its
Tariff. GRT shall not be obligated to award any capacity at a non-maximum
FERC-approved rate.
Capacity is available at the Gulf Run Zone 1 bidirectional meter (GRZ1Z2) and
the Gulf Run Zone 2 bidirectional meter (GRZ2Z1).
|
Please contact your GRT Marketing Representative
concerning additional questions, inquiries regarding other periods than
those shown above, or other receipt/delivery point combinations that may be
applicable to Firm Transportation service.
|
Brad Cherry
Brad.Cherry@energytransfer.com
|
Matt Brill Matt.Brill@energytransfer.com
|
|
|
|
Daniel Pena (seasonal)
Daniel.Pena@energytransfer.com
|